When it is forecast that one or more tolerances are to be exceeded, what should happen first?

  1. The next higher level of management will begin to execute management by exception
  2. The appropriate level of management must refer the matter to the next higher level
  3. The Project Plan will be replaced by a fallback plan
  4. The appropriate level of management will automatically produce and execute an Exception Plan to recover from the deviation without referral

Answer(s): B



Which product produced by the Project Manager would contain information on 'products completed in the period'?

  1. Product Status Account
  2. Checkpoint Report
  3. Highlight Report
  4. Exception Report

Answer(s): C



Which product would the Project Manager use for gathering Work Package progress information?

  1. Highlight Report
  2. Daily Log
  3. Checkpoint Report
  4. Product Status Account

Answer(s): C



Which of the following is FALSE regarding an Exception Report?

  1. It describes a forecast deviation of stage or project level tolerance
  2. It contains recovery options and a recommendation
  3. It replaces a Stage Plan or Project Plan
  4. It describes the consequences of the deviation

Answer(s): C