In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

  1. Product Description
  2. Team Plan
  3. Work Package
  4. Stage Plan

Answer(s): C

Explanation:

In PRINCE2®, a Work Package is the document where the Project Manager defines the time and cost tolerances for the work assigned to a Team Manager. The Work Package provides detailed information on the products to be delivered, the reporting requirements, and the tolerances within which the Team Manager operates.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a purpose of the Directing a Project process?

  1. Create and authorize the project mandate
  2. Ensure that work on products allocated to the team is authorized and agreed
  3. Control the day-to-day running of the project
  4. Delegate day-to-day management of the project to the Project Manager

Answer(s): D

Explanation:

The purpose of the Directing a Project process is for the Project Board to delegate the day-to-day management of the project to the Project Manager, providing the overall direction and management of the project lifecycle. This process is critical for enabling the Project Manager to run the project on behalf of the Project Board within the constraints set out by them.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a purpose of the Directing a Project process?

  1. Provide the information required to confirm if it is worthwhile to initiate a project
  2. Enable overall control of a project to be exercised by the Project Board
  3. Establish the level of control required by the Project Board after initiation.
  4. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved

Answer(s): B

Explanation:

The purpose of the Directing a Project process in PRINCE2 is to enable the Project Board to exercise overall control over the project while delegating day-to-day management of the project stages to the Project Manager. This ensures that the Project Board can make key decisions and remain accountable for the project's success while not being involved in the lower-level, day-to-day activities.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which is an objective of the Directing a Project process?

  1. Create and authorize the project mandate
  2. Provide management control and direction
  3. Control the day-to-day running of the project
  4. Provide accurate progress information to the Project Manager

Answer(s): B

Explanation:

An objective of the Directing a Project process is to provide management control and direction for the project. This involves making strategic decisions, providing overall guidance to the Project Manager, and ensuring the project remains aligned with organizational objectives and capable of delivering the benefits defined in the Business Case.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources






Post your Comments and Discuss PRINCE2 PRINCE2 Foundation exam with other Community members:

PRINCE2 Foundation Exam Discussions & Posts