Which of the following best defines an output?

  1. The information required for decision-making purposes
  2. The measurable improvement resulting from an outcome
  3. The result of the change derived from using the project's outputs
  4. Any one of the project's specialist products

Answer(s): D



Which of the following best defines a dis-benefit?

  1. A risk which occurs and subsequently impacts a stakeholder
  2. An outcome perceived as negative by one or more stakeholders which may occur during the project
  3. An outcome perceived as negative by one or more stakeholders which has actual consequences
  4. Any one of the project's issues which directly affects a stakeholder

Answer(s): B



Which statement regarding a project's outputs, outcomes and benefits is correct?

  1. All outputs have tangible benefits
  2. Outcomes are the long term results of business benefits
  3. Outputs are changes in the way the project's products are used
  4. Benefits are measurable improvements resulting from project outcomes

Answer(s): D



Which best describes the purpose of a Business Case?

  1. Used to define how and when a measurement of the project's benefits can be made
  2. Documents the justification for undertaking the project, based on estimated costs, the benefits to be gained and offset by any associated risks
  3. Allows the Project Board to manage by exception throughout the project through providing continuous justification
  4. Describes the specific risk management techniques and standards to be applied throughout the project

Answer(s): B