How should a project leader manage stakeholder expectations in an agile project?

  1. Establish a common vision and success criteria and involve all the stakeholders in the iteration reviews
  2. Invite stakeholders for the iteration reviews but do not include new stakeholders which may limit project success
  3. Involve all the stakeholders in iteration reviews but do not entertain all expectations of all stakeholders
  4. Communicate issues to all stakeholders via email and only communicate risks to internal stakeholders

Answer(s): A



A scrum master would like to provide information to key stakeholders on the daily resource and project activities.
Which tool should the Scrum master use to provide these updates?

  1. Shared vision statement and sprint goal
  2. Release burnup chart
  3. Velocity metrics
  4. Iteration burndown chart

Answer(s): D



After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.
If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?

  1. Stakeholders should have regularly been engaged to obtain feedback and reduce the functionality risk
  2. The team should have used the lean principle of delay, so that actual facts could be considered rather than assumptions and predictions
  3. Interdependent teams should have been engaged using a collaborative approach to identify and leverage the best support
  4. An owner should have been identified to obtain timely stakeholder feedback

Answer(s): A



During a project's last few sprints, an agile practitioner notices an increase in defects. A rootcause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.
What should the agile practitioner do?

  1. Inform the product owner's manager so that corrective action may be taken
  2. Communicate this to the product owner, and offer to help facilitate discussion with the team
  3. Encourage a team member to raise this during the retrospective to ensure that the product owner is aware
  4. Escalate this issue to the sponsor so that corrective action may be taken

Answer(s): B



Page 33 of 81



Post your Comments and Discuss PMI PMI-ACP exam with other Community members:

mustapha commented on August 14, 2024
good simulation
Anonymous
upvote

Ravi commented on March 28, 2024
I am from India. I wrote this exam last week and I passed. The study material is good. Saved me a lot of time. I was actually planning on a bootcamp but then I came across this site and decided to give a try. It worked out well.
INDIA
upvote

Krasen commented on June 15, 2023
Thank you for these questions and answers. The 50% discount code worked. I bouth 2 exams and I already passed one.
HONG KONG
upvote

Adam K commented on May 24, 2023
The stuff is really good. I do recommend it.
POLAND
upvote

Herath commented on March 18, 2022
I am happy to report that I passed my second exam today. Thank you guys for this helpful study package.
SINGAPORE
upvote

BBQ commented on December 30, 2021
It is a very useful information before going to your actual exam.
HONG KONG
upvote

Kristopher commented on January 27, 2019
I loved the payment part of the website. They do not ask for any personal information. Just the credit card number and date. Very desecrate. I like!
UNITED KINGDOM
upvote

Ivan Cheung commented on August 23, 2016
The material is useful and save me a lot of time to get the exam passed without any difficulty!!
HONG KONG
upvote