An agile project is in its eighth iteration out of 16. After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply.Which two actions should the project manager take? (Choose two.)
Answer(s): B,E
A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project.What should the project manager do to enhance the success of the project?
Answer(s): A
During the course of the project, several obstacles are identified that are preventing the project from moving forward.What should the project manager do to remove the obstacles?
Answer(s): B
The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project. If the project continues on the same path, it will consume twice the time and budget planned.What two actions can the project manager take to be more cost effective? (Choose two.)
Answer(s): A,D
A project manager is working with a Scrum team that is continually missing deadlines. The steering committee is concerned about the project as it is not clear that it will deliver the expected value. After some analysis, the project manager discovers there is a mismatch of competencies in one of the teams.What should the project manager do?