The Project Board have overall control at what level?

  1. Day-to-day control for a management stage within stage tolerance
  2. Work Package level within Work Package tolerance
  3. Project level within project tolerance
  4. All levels of plans and tolerances

Answer(s): C



What name is given to the permissible deviation allowed above and below a plan's target for time and cost without escalating the deviation to the next level of management?

  1. Concession
  2. Tolerance
  3. Contingency
  4. Allowance

Answer(s): B



If any type of issue or risk (or aggregation of them) cannot be resolved within the tolerances set by the Project Board, which of the following products would first be sent to the Project Board to inform them of this deviation?

  1. Exception Report
  2. End Stage Report
  3. Highlight Report
  4. Updated Risk and Issue Registers

Answer(s): A



Tolerance forms a key element of allowing the Project Board to manage by exception. Which of the following statements are correct regarding tolerance?
1. The Project Board sets project tolerances
2. Tolerances can be applied for Time, Cost, Scope, Quality, Benefit and Risk
3. The Project Manager sets Work Package tolerance
4. Cost tolerance should not be used to pay for authorized requests for change

  1. 1, 2, 3
  2. 1, 2, 4
  3. 1, 3, 4
  4. 2, 3, 4

Answer(s): D