Which of the following is a Project Board control?

  1. Project-level tolerance
  2. Stage-level tolerance
  3. Checkpoint Report
  4. Quality Register

Answer(s): B



Which level of management in the project management team has the ability to review progress and decide whether to continue, change or stop the project?

  1. Project Manager
  2. Project Board
  3. Team Manager
  4. Corporate or programme management

Answer(s): B



There should be at least two management stages in a PRINCE2 project. Which of the following options describes those stages?

  1. Initiation as the first stage, the remainder of the project as the second stage
  2. Initiation as the first stage, closure activities as the second stage
  3. Procurement as the first stage, design and implementation as the second stage
  4. Pre-project work as the first stage, initiation as the second stage

Answer(s): A



Please refer to section 10.3.2.1 in the PRINCE2 Manual. (Exception Plans are only produced if requested by the Project Board. Team Plans and the use of seperate people as Team Managers are optional in PRINCE2)

  1. Use of Team Managers
  2. Use of management stages
  3. Use of Exception Plans
  4. Use of Team Plans

Answer(s): B